In his Address to the Nation, President Kassym-Jomart Tokayev set the strategic objective of achieving a sustainable electricity surplus by 2029. In this regard, particular attention is being paid to developing new power generation capacity of strategic importance for strengthening the country's energy sovereignty.
During his visit to the construction site of the 1,113.4 MW Turkistan Combined-Cycle Power Plant in Sairam District, Nurlybek Nalibayev emphasized the significance of this large-scale project, which will help reduce electricity shortages in southern regions, bring new generating capacity online, and ensure a stable power supply to consumers. A total of 2,455 personnel are currently employed at the construction site, including 2,281 on the day shift and 174 on the night shift.
The main technological equipment, including gas and steam turbines and heat recovery steam generators (HRSGs), has been delivered to the site. All four Siemens gas turbine units have been installed. Construction and installation works are 62% complete, electrical network installation is 96% complete, and construction of the gas pipeline has been completed.
The project предусматривает seven wells, of which two currently provide a total of 960 m³ of water per day. The first phase of the power plant requires 240 m³ of water per day for its start-up.
In addition, a 3.1 km access road has been commissioned.
“This is an important facility that is under the direct supervision of the Head of State. Construction must not be delayed, and all work must be completed within the established deadlines. You stated that the trial start-up of the first unit is scheduled for the end of this year. In May 2027, 382 MW of generating capacity is expected to be supplied to the power grid, followed by another 382 MW in August. Thus, a total of 764 MW is planned to be commissioned by September.
Work must continue to accelerate. It may be appropriate to bring forward the deadlines currently scheduled for March to May 2028, expedite the project's implementation, and bring the plant to full capacity by the end of 2027. Once operational, this large power plant will be able to supply electricity to Turkistan Region, the city of Shymkent, and Zhambyl Region.
Construction progress has clearly accelerated significantly. At the beginning of the year, the completion rate was 15%, whereas it has now reached 62%. The Government and the regional administration are providing comprehensive support. Your task is to organize the work and fulfill the commitments you have undertaken,” the First Deputy Prime Minister stated.
The next stop on the working visit was the Sastobe Innovation Complex in Tulkibas District. This major investment project is aimed at developing the region's chemical industry and producing import-substituting products. The enterprise will have an annual production capacity of 400,000 tonnes of lime, 100,000 tonnes of caustic soda, 120,000 tonnes of polyvinyl chloride (PVC), 200,000 tonnes of calcium carbide, and 1 million tonnes of cement.
A lime production line was commissioned last year. Its products are currently being supplied to domestic metallurgical enterprises and construction materials manufacturers.
The commissioning schedules for subsequent phases of the investment project have been revised in line with financing availability, and issues related to project implementation have been thoroughly reviewed. The relevant government agencies have been instructed to identify financing sources, complete the construction of engineering infrastructure, and ensure the investment project is implemented within the established deadlines.
20 November 2026